How do I claim an extension of time on a construction contract in New Zealand?

Under NZS 3910:2023, give written notice of the circumstances to the Contract Administrator and the Independent Certifier within 20 working days of becoming aware of them, then give the period of extension you seek, in the same notice or soon after. Back it with a programme that shows the effect on the critical path (the chain of work that sets the finish date). Other contract forms set their own deadlines: under FIDIC 2017 you have 28 days, and missing them can cost you the claim.

The steps under NZS 3910:2023 (clause 10.3)

  1. 01Check the delay comes from a ground the contract recognises: a variation, inclement weather, a strike or lockout, loss or damage to the works, a flood, volcanic or seismic event, circumstances an experienced contractor could not reasonably foresee at tender and not your fault, or default by the Principal (cl 10.3.1).
  2. 02Give written notice of the circumstances to the Contract Administrator and the Independent Certifier within 20 working days after you become aware of them (cl 10.3.2(a)).
  3. 03Give the details of the period of extension you seek, in that first notice or in a second notice within a reasonable time (cl 10.3.2(b)).
  4. 04If the delay keeps going, you can give notice more than once, claiming a specific period each time (cl 10.3.3).
  5. 05You and the Contract Administrator try to agree the extension, and meet if either of you or the Independent Certifier asks. Once you agree, the Contract Administrator issues an instruction within 10 working days (cl 10.3.4).
  6. 06If you can't agree, the Independent Certifier decides whether you are fairly entitled and to how long, within 20 working days of a request or as soon as practicable after, and gives reasons (cl 10.3.5).

What the Independent Certifier weighs (clause 10.3.6)

  1. 01How far the delay has affected, or is likely to affect, the critical path. A delay to work that has spare time (float) may earn no extension.
  2. 02Whether you took reasonable steps to reduce the delay.
  3. 03The effect of any late notice: how late it was, what it cost the Principal or the works, and whether an earlier notice could have avoided or reduced the delay. A late notice does not automatically end the claim under NZS 3910:2023, but it can shrink it.

Time is not always money

  1. 01Under NZS 3910:2023 you get time-related costs only when the extension is for a variation or for the Principal's default. For the other grounds you get the time but not the money (cl 10.3.8).
  2. 02Under FIDIC 2017 (Red Book), notice of a claim is due as soon as practicable and no later than 28 days after you became aware, or should have become aware, of the event. Miss it and the time and money for that event are lost (sub-cl 20.2.1).
  3. 03If you suspend work for non-payment under the Construction Contracts Act, you are entitled to an extension of time for the suspension, but the Act alone does not give you the costs (s 24A(2)(c)).
Free Word templateExtension of Time Claim Template (NZS 3910:2023)Get it →

From practice

Send the first notice as soon as you know what happened, even before you know how many days you will need. The period can follow in a second notice. A short notice sent on time is worth more than a perfect one sent late.

Sources

Checked on 10 November 2026 against NZS 3910:2023 clauses 10.3.1 to 10.3.8, the FIDIC Conditions of Contract for Construction (2017) sub-clause 20.2.1 and the Construction Contracts Act 2002 s 24A. General information only, not legal advice. Your special conditions may change these times, so check your contract.

Have a contract, claim or programme that needs attention?

Tell us where the project is and what is at stake. We will come back with a clear view of your position and the next steps.

Book a free 30 minute call (opens in a new tab)

How we work

  1. Review

    We first secure any notice deadlines about to expire, then review your documents: the contract, the BOQ and the project records.

  2. Assess

    We test the assumptions, map entitlements, risks and dependencies, and put honest ranges on cost and time.

  3. Advise

    You get clear options and a recommendation: what changed, why it matters, what to decide and by when.

  4. Deliver

    We prepare what is needed and keep it on track, from notices, claims and programmes to reporting, procurement and AI workflows. That can be a single task or an ongoing role for the whole contract, such as Independent Certifier, contract administrator or financial management of claims and invoicing.

Not sure where to start? Payment Claim Health Check →