Case study · With Ventia
Kōwhai Park Solar Farm: commercial control of an $80M NEC scope
- Value
- $80M EPC scope of a $300M solar farm
- Size
- 170 MWdc, two sites, two substations
- Contract
- NEC
- Location
- Christchurch
The challenge
A grid connected solar farm built across two sites, with long lead equipment from around 45 suppliers worldwide. Under NEC, money and time depend on notices and records, so the commercial side had to be set up properly from the start.
What was done
- Ran the project commercial function
- Built the governance, risk and reporting framework from scratch
- Built and maintained the project cashflow using earned value, with monthly cost to complete forecasts
- Certified progress claims of up to $3M a month
- Oversaw 67 procurement packages, including long lead equipment, across two sites
- Prepared a structured negotiation strategy for variations and claims
The result
$4M+
recovered in variations and claims
~2 months
extension of time
67
procurement packages managed
Delivered in an earlier role with Ventia, not as a CMPC engagement.
What this means for your project
- Set up the claims and notice process before the first event, not after it
- Tie the programme to the money with earned value, so delay and cost are argued together
- Go into negotiation with a written strategy and the records already assembled