Upcoming civil and water projects in Waikato
27 public civil and water projects of $1 million or more are due to go to tender or start construction in Waikato in the next 12 months, worth at least $1.2 billion. 13 are tendering now or about to be awarded. The biggest buyer is Iawai – Flowing Waters Limited, with 7 projects.
27
projects of $1M or more
$1.2 billion
at least, by value band
12
worth $10M or more
17 / 10
civil / water
When the work comes to market
- Tendering now or about to be awarded13
- Tender expected within 6 months7
- Tender expected in 6 to 12 months0
- Construction starting in the next 12 months7
The 12 largest upcoming projects
Ranked by value band. 15 smaller projects are not listed here.
| Project | Buyer | Value band | Timing |
|---|---|---|---|
| RoNS SH1 Cambridge to Piarerecivil | NZ Transport Agency | $1B to $5B | Construction starts within 6 months |
| SH26 Kirikiri Stream Bridge Replacementcivil | NZ Transport Agency | $50M to $100M | Construction starts in 6 to 12 months |
| SH3 Awakino Gorgecivil | NZ Transport Agency | $50M to $100M | Construction starts within 6 months |
| IAF – Bulk Water Reticulationwater | Iawai – Flowing Waters Limited | $25M to $50M | Tender within 6 months |
| Cambridge Road intersection and new Collector Road C4 & C11 Growthcivil | Waipā District Council | $10M to $25M | Tender within 6 months |
| Flood Management Programmecivil | Iawai – Flowing Waters Limited | $10M to $25M | Tender within 6 months |
| Hautapu & Hannon Road Urbanisation C8, C9 & C10 Growthcivil | Waipā District Council | $10M to $25M | Tendering now |
| Hautapu Urbanization stage 1 C8, C9 & C10 Growthcivil | Waipā District Council | $10M to $25M | Tendering now |
| Road Maintenance Contractcivil | Ōtorohanga District Council | $10M to $25M | Tender within 6 months |
| SH25 corridor targeted resiliencecivil | NZ Transport Agency | $10M to $25M | Construction starts within 6 months |
| TRF SH1 Bulli Point Te Poporocivil | NZ Transport Agency | $10M to $25M | Construction starts in 6 to 12 months |
| Waiora WTP Upgradewater | Iawai – Flowing Waters Limited | $10M to $25M | Contract about to be awarded |
Who is buying
- Iawai – Flowing Waters Limited7 · $53 million+
- Waipā District Council6 · $37 million+
- NZ Transport Agency5 · $1.1 billion+
- Waikato Regional Council3 · $11 million+
- Taupō District Council2 · $6 million+
- Ōtorohanga District Council1 · $10 million+
- South Waikato District Council1 · $5 million+
- Waitomo District Council1 · $5 million+
- Matamata-Piako District Council1 · $1 million+
How to use this list
- Projects tendering now or within six months are the ones to plan resources for today: check you hold the buyer's pre-qualification and that your team can price in the window.
- Read the conditions of contract as soon as the tender documents land. Special conditions often change notice periods and payment terms from the standard form.
- Set up a notice register before work starts, so variations and delays are notified on time from day one.
Get the free tender report sample
The free sample shows who has been winning and buying public work in this region over recent years, so you can see where your firm sits before these projects come to market.
As at October 2026. Public civil and water projects with an estimated value of $1 million or more, due to go to tender or start construction within 12 months. Values are bands, so totals use the bottom of each band and are a floor, not the full spend. Timings move; check the buyer's own notice before you price.