Do working days under the Construction Contracts Act include the Christmas break?

No. For the payment and adjudication time limits in the Construction Contracts Act, 24 December to 5 January are not working days, so those limits stop for that period and start again afterwards. If your contract sets its own time limit, read how the contract defines a working day.

What counts as a working day under the Act

  1. 01A working day is any day except a Saturday or Sunday, the public holidays listed in the Act, and the anniversary day of the province where the work is (s 5).
  2. 02The listed holidays are Waitangi Day, Good Friday, Easter Monday, Anzac Day, the Sovereign's birthday, Matariki Observance Day and Labour Day. When Waitangi Day or Anzac Day falls on a weekend, the following Monday is excluded too (s 5).
  3. 03The Christmas period depends on the section. For ss 18, 22, 24A, 33, 35 to 37A, 46, 47, 59 and 66 it runs from 24 December to 5 January. For ss 71B, 74 and 75 it runs from 25 December to 15 January (s 5). Check which section your time limit comes from.

Which time limits this changes

  1. 01The default time to give a payment schedule: 20 working days after the claim is served, if the contract is silent (s 22).
  2. 02The default due date for payment: 20 working days after the claim is served, if the contract is silent (s 18).
  3. 03The 5 working days that must pass after a notice of intention to suspend work (s 24A).
  4. 04The time limits in the adjudication process under ss 33, 35 to 37A, 46 and 47.

A worked example

  1. 01A payment claim is served on Thursday 3 December 2026 and the contract sets no time.
  2. 02Fourteen working days run from 4 to 23 December.
  3. 03The count stops from 24 December to 5 January.
  4. 04It starts again on Wednesday 6 January 2027, and the twentieth working day is Wednesday 13 January 2027. That is 41 calendar days after the claim was served.

From practice

Work out the real date the day a claim arrives in December, and put it in the diary with the name of whoever is covering while the office is closed.

Sources

Checked against the Act on 11 November 2026. General information only, not legal advice. Your contract may set different times, so check it.

Have a contract, claim or programme that needs attention?

Tell us where the project is and what is at stake. We will come back with a clear view of your position and the next steps.

Book a free 30 minute call (opens in a new tab)

How we work

  1. Review

    We first secure any notice deadlines about to expire, then review your documents: the contract, the BOQ and the project records.

  2. Assess

    We test the assumptions, map entitlements, risks and dependencies, and put honest ranges on cost and time.

  3. Advise

    You get clear options and a recommendation: what changed, why it matters, what to decide and by when.

  4. Deliver

    We prepare what is needed and keep it on track, from notices, claims and programmes to reporting, procurement and AI workflows. That can be a single task or an ongoing role for the whole contract, such as Independent Certifier, contract administrator or financial management of claims and invoicing.

Not sure where to start? Payment Claim Health Check →