What must a payment claim include under the Construction Contracts Act?

A payment claim must be in writing, identify the contract, the work and the period, state the claimed amount and due date, show how the amount was calculated, and state that it is made under the Construction Contracts Act. It must also come with an outline of how to respond and what happens if the payer doesn't respond or pay.

The checklist (section 20)

  1. 01In writing (s 20(2)(a)).
  2. 02Enough detail to identify the construction contract (s 20(2)(b)).
  3. 03The construction work and the period the payment covers (s 20(2)(c)).
  4. 04The claimed amount and the due date for payment (s 20(2)(d)).
  5. 05How you calculated the claimed amount (s 20(2)(e)).
  6. 06A statement that it is made under the Construction Contracts Act 2002 (s 20(2)(f)).

What must go with it

  1. 01An outline of the process for responding to the claim (s 20(3)(a)).
  2. 02An explanation of what happens if the payer doesn't respond, or doesn't pay the claimed or scheduled amount in full (s 20(3)(b)).
  3. 03Both in writing and in the prescribed form, if there is one (s 20(4)).

From practice

Send a payment claim, not just an invoice. Attach the backup the payer will ask for anyway: signed timesheets, material invoices and a breakdown that matches your contract's schedule of prices.

Sources

Checked against the Act on 30 October 2026. General information only, not legal advice. Your contract may set different times, so check it.

Have a contract, claim or programme that needs attention?

Tell us where the project is and what is at stake. We will come back with a clear view of your position and the next steps.

Book a free 30 minute call (opens in a new tab)

How we work

  1. Review

    We first secure any notice deadlines about to expire, then review your documents: the contract, the BOQ and the project records.

  2. Assess

    We test the assumptions, map entitlements, risks and dependencies, and put honest ranges on cost and time.

  3. Advise

    You get clear options and a recommendation: what changed, why it matters, what to decide and by when.

  4. Deliver

    We prepare what is needed and keep it on track, from notices, claims and programmes to reporting, procurement and AI workflows. That can be a single task or an ongoing role for the whole contract, such as Independent Certifier, contract administrator or financial management of claims and invoicing.

Not sure where to start? Payment Claim Health Check →