What is NZS 3910:2023 and how does it work?

NZS 3910:2023 is New Zealand's standard contract for building and civil engineering work where the client's team provides the design and the contractor builds it. It sets who gives instructions and who makes decisions, how payment claims are made and paid, how variations and extensions of time are claimed, and how disputes are settled. The 2023 edition replaced the old Engineer to the Contract with two roles: a Contract Administrator, who acts for the client, and an Independent Certifier, who decides matters between the parties fairly and impartially.

Who does what under NZS 3910:2023

  1. 01The client (the Principal) must have a suitably experienced Contract Administrator and Independent Certifier in place at all times, and both must act reasonably and in good faith (cl 6.1.1).
  2. 02The Contract Administrator acts for the Principal and gives the contractor instructions. Instructions must be in writing, or confirmed in writing as soon as practicable, and must say whether or not they are a variation (cl 6.2.1 and 6.3.2).
  3. 03The Independent Certifier decides matters between the parties fairly, impartially and independently of both: valuing the work, certifying payment schedules, deciding and valuing variations, deciding extensions of time and issuing completion certificates (cl 6.2.2).
  4. 04The Independent Certifier acts as the Principal's agent only for receiving payment claims, adding the Principal's notified deductions and issuing payment schedules (cl 6.2.3).
  5. 05One person can hold both roles. Their names are in the Specific Conditions, and each appointment must be one named person, not a firm (cl 6.1.2 and 6.1.5).
  6. 06If the Contract Administrator or Independent Certifier fails to do their job properly and that delays the contractor or adds cost, the failure is treated as a variation (cl 6.3.3).

Payment claims and payment schedules (clause 12)

  1. 01The contractor serves payment claims on the Independent Certifier, with a copy to the Principal and the Contract Administrator. Unless the contract says otherwise, each claim covers a period of at least one month (cl 12.1.1 and 12.1.2).
  2. 02Each claim identifies the contract, the period and the work, states the amount and how it was worked out, and gives a due date 17 working days after the claim is served. To be a claim under the Construction Contracts Act, it must also say so and include what the Act requires (cl 12.1.3).
  3. 03Within 7 working days of the claim, the Independent Certifier issues a provisional payment schedule, with reasons for any difference from the claimed amount (cl 12.2.2).
  4. 04Within 10 working days, the Principal may notify deductions, with reasons. The Independent Certifier then issues a replacement payment schedule within 12 working days. If none is issued, the provisional schedule stands (cl 12.2.4 to 12.2.6).
  5. 05The Principal pays the scheduled amount plus GST within 17 working days of the claim being served (cl 12.2.7).

Variations, early warnings and extensions of time

  1. 01The contractor must not change the works without a written instruction from the Contract Administrator (cl 9.2.1).
  2. 02If an instruction is not called a variation but you think it is one, give written notice within 20 working days, or as soon as practicable after (cl 9.2.2).
  3. 03If something else happens that you think should be a variation, give written notice within 20 working days of becoming aware of it, or as soon as practicable after (cl 9.2.3).
  4. 04Everyone must give an early warning in writing as soon as they become aware of anything likely to change the contract price or delay completion materially (cl 6.10.1). If the contractor stays silent when it should have warned, a resulting variation can be valued as if the warning had been given and had reduced the impact (cl 6.10.3).
  5. 05For an extension of time, give written notice of the circumstances within 20 working days of becoming aware of them, then the period you seek (cl 10.3.2).

When you disagree with a decision

  1. 01Ask the Independent Certifier to review the matter, instruction or decision. The request is in writing, copied to the other party and the Contract Administrator, made within 3 months, with your reasons, and states that it is made under clause 6.4.1 (cl 6.4.1).
  2. 02The Independent Certifier answers with a further decision within 20 working days, or as soon as practicable (cl 6.4.3).
  3. 03Still not satisfied? Ask for another review or for a Final Decision, within 3 months. The Final Decision is due within 20 working days (cl 6.4.4 to 6.4.6).
  4. 04A dispute about a Final Decision can go to arbitration. Before that, senior people on both sides try to settle it in good faith, and the parties can agree to mediate at any stage (cl 13.1.1, 13.2.1 and 13.3.2).
  5. 05Adjudication under the Construction Contracts Act stays open throughout. Any party to a construction contract can refer a dispute to adjudication, and the contract cannot take that right away (Construction Contracts Act ss 12 and 25).

What to check before you sign

  1. 01Which edition the contract names. The 2013 edition still uses the Engineer to the Contract, and its roles and processes differ.
  2. 02The Specific Conditions: who the Contract Administrator and Independent Certifier are, and whether one person holds both roles.
  3. 03Any changes to the standard time limits. Special conditions often shorten or lengthen them.
  4. 04Any design you are asked to do. Under NZS 3910:2023 it must be listed in the Specific Conditions (cl 5.2.1).
Free Fillable PDFNZS 3910:2023 Notice TrackerGet it →

From practice

On day one, read the Specific Conditions and put every NZS 3910 time limit for your job into one diary. A good claim with a late notice is much harder to win than a modest claim sent on time.

Sources

Checked on 18 November 2026 against NZS 3910:2023 clauses 5.2.1, 6.1 to 6.4, 6.10, 9.2, 10.3.2, 12.1, 12.2 and 13.1 to 13.3, and the Construction Contracts Act 2002 ss 12 and 25. General information only, not legal advice. Your Specific Conditions may change these terms and times, so check your contract.

Have a contract, claim or programme that needs attention?

Tell us where the project is and what is at stake. We will come back with a clear view of your position and the next steps.

Book a free 30 minute call (opens in a new tab)

How we work

  1. Review

    We first secure any notice deadlines about to expire, then review your documents: the contract, the BOQ and the project records.

  2. Assess

    We test the assumptions, map entitlements, risks and dependencies, and put honest ranges on cost and time.

  3. Advise

    You get clear options and a recommendation: what changed, why it matters, what to decide and by when.

  4. Deliver

    We prepare what is needed and keep it on track, from notices, claims and programmes to reporting, procurement and AI workflows. That can be a single task or an ongoing role for the whole contract, such as Independent Certifier, contract administrator or financial management of claims and invoicing.

Not sure where to start? Payment Claim Health Check →