My payment schedule cut my claim. What can I do?

First check the payment schedule. If it arrived late or not at all, you may be owed the whole claim. If it arrived in time and meets the Act, the scheduled amount has to be paid by the due date, and you can dispute the rest, including at adjudication.

Check the schedule

  1. 01Timing: it must be given within the time your contract sets, or 20 working days after the claim was served if the contract is silent. If it was not given in time, the payer becomes liable to pay the claimed amount (s 22).
  2. 02Basics: it must be in writing, identify your payment claim and state a scheduled amount (s 21(2)).
  3. 03Reasons: if the scheduled amount is less than you claimed, it must show how it was calculated, why it differs, and why anything is being withheld (s 21(3)).
  4. 04"We have not been paid yet" is not a valid reason. A pay when paid clause has no legal effect and cannot be used to withhold payment that is due (s 13).

Get the scheduled amount paid

  1. 01The amount in the schedule is due by the due date, even while you argue about the rest.
  2. 02If it is not paid, you can recover it as a debt in court and can serve notice that you intend to suspend work (s 24).
  3. 03If it is still unpaid 5 working days after that notice, you may suspend work (s 24A).

Dispute the difference

  1. 01Make a table with one line per deduction: what you claimed, what they scheduled, the reason they gave and your evidence.
  2. 02Send it to them and ask for a meeting.
  3. 03Check your contract's dispute clause for its steps and time limits.
  4. 04Any party to a construction contract has the right to refer a dispute to adjudication, and a disagreement about whether an amount is payable or the reasons for not paying it is one example the Act gives (s 25).

From practice

Deductions have to be calculated and explained. Any line in the schedule with no reason next to it is the first one to challenge (s 21(3)).

Sources

Checked against the Act on 11 November 2026. General information only, not legal advice. Your contract may set different times, so check it.

Have a contract, claim or programme that needs attention?

Tell us where the project is and what is at stake. We will come back with a clear view of your position and the next steps.

Book a free 30 minute call (opens in a new tab)

How we work

  1. Review

    We first secure any notice deadlines about to expire, then review your documents: the contract, the BOQ and the project records.

  2. Assess

    We test the assumptions, map entitlements, risks and dependencies, and put honest ranges on cost and time.

  3. Advise

    You get clear options and a recommendation: what changed, why it matters, what to decide and by when.

  4. Deliver

    We prepare what is needed and keep it on track, from notices, claims and programmes to reporting, procurement and AI workflows. That can be a single task or an ongoing role for the whole contract, such as Independent Certifier, contract administrator or financial management of claims and invoicing.

Not sure where to start? Payment Claim Health Check →