What is the difference between NZS 3910 and NZS 3916?
NZS 3910 is New Zealand's standard contract for building and civil works where the client's team does the design and the contractor builds it. NZS 3916 is the design and construct version: Standards New Zealand describes it as similar to NZS 3910 but adapted for when the contractor is responsible for design as well as construction. The current editions are NZS 3910:2023 and NZS 3916:2025.
Which one fits your project
- 01The client's designers produce the drawings and specifications and the contractor builds them: NZS 3910:2023.
- 02NZS 3910:2023 can still give the contractor part of the design. The parts must be named in the Specific Conditions, and the contractor designs the temporary works unless the Specific Conditions say otherwise (cl 5.2.1 and 5.2.2).
- 03The contractor designs and builds the works: NZS 3916:2025.
- 04Ongoing work over a set period, such as maintenance: NZS 3917:2025, the fixed term version of the same family.
What they share
- 01NZS 3916:2025 is based on NZS 3916:2013 and NZS 3910:2023, and carries across the changes made in the 2023 edition.
- 02Both drop the old Engineer to the Contract and split that job into two roles: a Contract Administrator, who acts for the client and gives instructions, and an Independent Certifier, who decides matters between the parties fairly and impartially, such as valuing work, variations, extensions of time and completion certificates.
- 03The two roles can be held by the same person, so check who is named in the Specific Conditions (NZS 3910:2023 cl 6.1.2).
What to check before you sign
- 01Which edition the contract names. Some clients still use the 2013 editions, and the roles and processes differ.
- 02On NZS 3910:2023, read Specific Condition 5.2. It is where any contractor design is listed. Design you are asked to do that isn't listed there is worth raising in writing.
- 03If you design, the professional indemnity insurance the contract asks for. NZS 3910:2023 requires it for contractor's design where the Specific Conditions say so (cl 8.6.1).
- 04On design and construct, what the client's requirements actually say. They set what your design has to achieve, so gaps and vague wording become your risk.
From practice
Before you price, list every part of the design and write down who owns it. Design arguments usually start with a part nobody clearly owned.
Checked on 10 November 2026 against NZS 3910:2023 (foreword and cl 5.2.1, 5.2.2, 6.1.2 and 8.6.1) and the Standards New Zealand foreword to NZS 3916:2025 (consultation draft, January 2025). General information only, not legal advice. Your special conditions may change these terms, so check your contract.