How do I respond to a payment claim in New Zealand?
Send the payee a payment schedule in writing before your deadline. It must identify the payment claim and state the amount you will pay. If that is less than the claim, show how you worked it out and why. Then pay the amount you scheduled by the due date.
Five steps when a payment claim arrives
- 01Write down the date the claim was served and work out your deadline that day. It is the time your contract sets for a payment schedule. If the contract says nothing, it is 20 working days after the claim was served (s 22).
- 02Check the claim. Under the Act it must be in writing, identify the contract, the work and the period, state the amount and due date, show how the amount was worked out, and say it is made under the Act (s 20(2)). It should also come with an outline of how to respond and what happens if you don't (s 20(3)).
- 03Decide what you will pay. Value the work claimed against the contract, and note every amount you disagree with or are holding back, with the reason for each one.
- 04Write the payment schedule. It must be in writing, identify the payment claim and state the scheduled amount (s 21(2)). If you are paying less than the claim, show how you calculated the amount, why it differs from the claim, and why you are holding anything back (s 21(3)).
- 05Serve it before the deadline in a way you can prove: hand it over, leave it at their place of business, or post it to their business address (s 80), plus any method your contract requires. Keep proof of when it arrived.
After you send it
- 01Pay the amount you scheduled by the due date. If you don't, the payee can recover the unpaid part as a debt in court and can give notice that it intends to suspend work (s 24).
- 02The due date is usually set by your contract. If the contract is silent, payment is due 20 working days after the claim was served (s 18).
- 03If you send no payment schedule in time, you become liable to pay the full claimed amount on the due date, whatever you think the work is worth (s 22).
- 04If the two of you still disagree about the amount, either party can refer the dispute to adjudication (s 25).
From practice
Send a payment schedule even when you think the claim is wrong or invalid. A schedule that says so, on time and with your reasons, protects you. Silence can leave you owing the full amount.
Sources
- Construction Contracts Act 2002, ss 18, 20, 21, 22, 24, 25 and 80 (legislation.govt.nz)
Checked against the Act on 13 November 2026. General information only, not legal advice. Your contract may set different times, so check it.